Some of the information on this Web page has been provided by external sources. The Government of Canada is not responsible for the accuracy, reliability or currency of the information supplied by external sources. Users wishing to rely upon this information should consult directly with the source of the information. Content provided by external sources is not subject to official languages, privacy and accessibility requirements.

Claims and Abstract availability

Any discrepancies in the text and image of the Claims and Abstract are due to differing posting times. Text of the Claims and Abstract are posted:

  • At the time the application is open to public inspection;
  • At the time of issue of the patent (grant).
(12) Patent Application: (11) CA 2372809
(54) English Title: METHOD AND INSTALLATION WITH SMELTING AND REDUCTION CYCLONE AND A COUPLED LOWER FURNACE FOR UTILISING RESIDUAL MATERIAL CONTAINING IRON AND HEAVY METALS AND OPTIONALLY IRON ORE
(54) French Title: PROCEDE ET DISPOSITIF UTILISANT UN CYCLONE DE FUSION/REDUCTION ET UN FOUR INFERIEUR ET PERMETTANT DE VALORISER DES MATIERES RESIDUELLES CONTENANT DU FER ET DES METAUX LOURDS ET/OUDES FINES DE MINERAI DE FER
Status: Deemed Abandoned and Beyond the Period of Reinstatement - Pending Response to Notice of Disregarded Communication
Bibliographic Data
(51) International Patent Classification (IPC):
  • C21B 13/14 (2006.01)
  • C21B 13/00 (2006.01)
  • C21B 13/12 (2006.01)
  • C21C 5/56 (2006.01)
  • C22B 5/14 (2006.01)
  • C22B 7/02 (2006.01)
(72) Inventors :
  • PESL, JOSEF (Austria)
  • SAUERT, FRIED (Austria)
  • FLEISCHANDERL, ALEXANDER (Austria)
(73) Owners :
  • VOEST-ALPINE INDUSTRIEANLAGENBAU GMBH
(71) Applicants :
  • VOEST-ALPINE INDUSTRIEANLAGENBAU GMBH (Austria)
(74) Agent: NORTON ROSE FULBRIGHT CANADA LLP/S.E.N.C.R.L., S.R.L.
(74) Associate agent:
(45) Issued:
(86) PCT Filing Date: 2000-03-28
(87) Open to Public Inspection: 2000-11-23
Availability of licence: N/A
Dedicated to the Public: N/A
(25) Language of filing: English

Patent Cooperation Treaty (PCT): Yes
(86) PCT Filing Number: PCT/EP2000/002702
(87) International Publication Number: WO 2000070101
(85) National Entry: 2001-11-08

(30) Application Priority Data:
Application No. Country/Territory Date
A 865/99 (Austria) 1999-05-14

Abstracts

English Abstract


The invention relates to a method and installation for utilising residual
material which contains iron, heavy metals and optionally iron ore. In said
method, the following take place: residual material and optionally the iron
ore is introduced into a smelting cyclone (1) with a backflow and a base
opening which has a narrowed section. Reducing agents and oxygen are
additionally introduced into the smelting cyclone (1) and are subjected to
swirling. Iron is reduced at least to FeO in the smelting cyclone (1), heavy
metals are reduced to metals in the smelting cyclone (1) and are converted
into the gas phase by evaporation. The resulting gas which optionally contains
heavy metals, the partially reduced iron and the slag are transferred to a
furnace (5) which is directly adjacent. Energy, in electrical form is then
supplied to said furnace (5), preferably using a direct electric arc. Reducing
agents and oxygen, or oxygen-enriched air is then introduced into the furnace
(5) and the iron is completely reduced and melted in the furnace (5). The
evaporated heavy metals are condensed outside the furnace (5), whereby the
iron can be subjected to further processing and a deposition of the residual
materials is avoided.


French Abstract

La présente invention concerne un procédé et un dispositif permettant de valoriser des matières résiduelles contenant du fer et des métaux lourds et éventuellement du minerai de fer. Ledit procédé consiste à amener les matières résiduelles et éventuellement le minerai de fer dans un cyclone de fusion (1) à reflux qui comporte une ouverture de fond (3) présentant un rétrécissement, à ajouter et mettre en tourbillonnement des agents de réduction et de l'oxygène dans ledit cyclone de fusion (1), à induire la réduction du fer dans ledit cyclone de fusion (1) pour donner au moins FeO, à induire la réduction des métaux lourds dans ledit cyclone de fusion (1) pour donner des métaux et à les convertir en phase gazeuse par évaporation, à transporter le gaz ainsi produit contenant éventuellement des métaux lourds, le fer partiellement réduit et les scories dans un four (5) directement adjacent, à alimenter ledit four (5) en énergie électrique, de préférence par un arc électrique direct, à amener dans ledit four (5) des agents de réduction et de l'oxygène ou de l'air enrichi en oxygène, à achever la réduction et induire la fusion du fer dans ledit four (5) et à induire la précipitation des métaux lourds évaporés hors dudit four (5), le fer pouvant ainsi être soumis à un traitement ultérieur et un dépôt des matières résiduelles étant ainsi évité.

Claims

Note: Claims are shown in the official language in which they were submitted.


-16-
Claims
1. A process for utilizing iron-containing and heavy-
metal-containing remainder materials and, if
appropriate, iron ore, characterized by the combination
of the following features:
- the remainder materials and, if appropriate, the
iron ore are introduced into a melting cyclone (1)
with return flow,
- reducing agents and oxygen are additionally
introduced into the melting cyclone (1) and are
made turbulent,
- in the melting cyclone (1), iron is reduced at
least to FeO,
- in the melting cyclone (1), heavy metals are
reduced to form metals and are converted into the
gas phase by vaporization,
- the resulting gas, which may contain heavy metals,
the partially reduced iron and the slag are
transferred into a directly coupled furnace (5),
- electrical energy is supplied to the furnace (5),
- reducing agents and oxygen or oxygen-enriched air
are introduced into the furnace (5),
- iron is fully reduced and partially melted in the
furnace (5), and
- the vaporized heavy metals are precipitated
outside the furnace (5).
2. The process as claimed in claim 1, characterized in
that the reducing agents are introduced in solid,
liquid or gaseous form.
3. The process as claimed in claim 1 or 2,
characterized in that coal or carbon-containing waste
materials are used as reducing agents.
4. The process as claimed in one or more of claims 1 to
3, characterized in that the reducing agents (which at

-17-
least in part are formed by fine particles) and/or the
oxygen are introduced into the furnace (5) via below-
bath blowing nozzles (12).
5. The process as claimed in one or more of claims 1 to
4, characterized in that the reducing agents and/or the
oxygen are introduced into the furnace (5) via a lance
(15) which is immersed in a slag layer (8).
6. The process as claimed in one or more of claims 1 to
5, characterized in that the electrical energy is
introduced into the furnace (5) via a direct arc.
7. The process as claimed in one or more of claims 1 to
6, characterized in that iron and slag are tapped off
separately from the furnace (5) via tapping holes (9
and 10).
8. The process as claimed in one or more of claims 1 to
7, characterized in that the heavy-metal-containing gas
is afterburned directly at the gas outlet and, in the
process, the heavy metals are brought into a solid,
oxidic form and are then separated off.
9. The process as claimed in one or more of claims 1 to
8, characterized in that the off-gas is extracted from
the furnace (5), and the heavy-metal-containing gas is
introduced into the extracted off-gas.
10. The process as claimed in one or more of claims 1
to 9, characterized in that heat from the melting
cyclone (1) is used to evaporate cooling water.
11. The process as claimed in one or more of claims 1
to 10, characterized in that heat from the furnace (5)
is used to evaporate cooling water.

-18-
12. The process as claimed in one or more of claims 1
to 11, characterized in that off-gas from the furnace
(5) is afterburned together with the heavy-metal-
containing gas and is then cooled, during which process
a water used for cooling is evaporated.
13. The process as claimed in one or more of claims 1
to 12, characterized in that the iron-containing
remainder material used is fine ore, in particular with
a fraction of ultrafine particles, preferably
originating from iron ore beneficiation and/or the
fines from a pelletizing operation.
14. A plant for utilizing iron-containing and heavy-
metal-containing remainder materials and, if
appropriate, iron ore, using the process as claimed in
one or more of claims 1 to 13, characterized by the
combination of the following features:
- a melting cyclone (1) which has a bottom opening
(3) with a constriction and feeds for iron-
containing and heavy-metal-containing remainder
materials and, if appropriate, iron ore and for
reducing agents and oxygen which open into the
melting cyclone (1),
- a furnace (5) with a feed for electrical energy,
- feeds for feeding reducing agents and oxygen or
oxygen-enriched air into the furnace (5), and
- an off-gas line which leads out of the furnace (5)
to a precipitation device for heavy-metal-
containing gas escaping from the furnace (5).
15. The plant as claimed in claim 14, characterized in
that the furnace (5) is equipped with at least one
electrode (11, 11', 11") which projects into the
furnace (5).
16. The plant as claimed in claim 14 or 15,
characterized in that the furnace (5) is provided with

19
blowing nozzles (12) for reducing agents and/or oxygen,
which are at least partially below the level of the
metal bath in the furnace (5) and to which feeds for
reducing agents and/or oxygen lead.
17. The plant as claimed in one or more of claims 14 to
16, characterized in that the furnace (5) is provided
with openings for lances (15) for blowing in reducing
agent and/or oxygen.
18. The plant as claimed in one or more of claims 14 to
17, characterized in that a feed (16) for a coarse
fraction of a reducing agent or remainder material
opens into the furnace (5).
19. The plant as claimed in one or more of claims 14 to
18, characterized in that a tapping hole (9) for iron
and a tapping hole (10) for slag are provided in the
furnace (5).
20. The plant as claimed in one or more of claims 14 to
19, characterized in that a connecting line (6) is
arranged between the bottom opening (3) of the melting
cyclone (1) and the furnace (5).
21. The plant as claimed in one or more of claims 14 to
20, characterized in that an intermediate chamber (20),
which if appropriate is in the form of an off-gas line,
is arranged on a wall (13) of the furnace (5), into
which intermediate chamber the connecting line (6)
which connects the bottom opening (3) to the furnace
(5) opens.
22. The plant as claimed in one or more of claims 14 to
21, characterized in that the off-gas line from the
furnace (5) opens into a heat exchanger, preferably
into a steam boiler (17).

-20-
23. The plant as claimed in claim 22, characterized in
that a hot-air line leads from the heat exchanger to a
dryer (23), to which sludge is fed, which sludge, in
the dried state, can be fed to the melting cyclone (1)
as remainder material via a transport line.
24. The plant as claimed in one or more of claims 14 to
23, characterized in that the melting cyclone (1) is
equipped with a cooling device, preferably with an
evaporation cooling device.
25. The plant as claimed in or more of claims 14 to 24,
characterized in that the furnace (5) is equipped,
above the metal level, with a cooling device,
preferably an evaporation cooling device.
26. The plant as claimed in one or more of claims 14 to
25, characterized in that an afterburning device (21)
for off-gas emerging from the furnace (5) is provided
in the off-gas line which leads out of the furnace or
at the point where this line opens into the furnace
(5).

Description

Note: Descriptions are shown in the official language in which they were submitted.


CA 02372809 2001-11-08
Method and Installation with Smelting and Reduction
Cyclone and a Coupled Lower Furnace For Utilising
Residual Material Containing Iron and Heavy Metals
and Optionally Iron Ore
The invention aerates to a process and a plant for
utilizing iron-containing and heavy-metal-containing
remainder materials and, if appropriate, iron ore.
A major problem of the iron- and steelmaking industry
is the continuous production of quantities of iron-
containing and heavy-metal-containing remainder
materials, such as for example furnace dusts, sludges,
rolling scale and the like, which are only available
for reuse with considerable outlay and therefore are
generally landfilled without the benefit being
extracted from their materials of value.
For ecological and economic reasons, there is a need to
separate the iron which is present in the remainder
materials from its accompanying metals and to return it
to the iron- or steelmaking process.
One process of the type described in the introduction
is the INMETCO process. In this process, iron-rich
metallurgical remainder materials are agglomerated with
solid reducing agents to form unburned, so-called
"green" pellets and are reduced in a rotary hearth
furnace, so that the heavy metals are vaporized, are
extracted with the off-gas and are then melted down or
optionally hot-briquetted in a melting furnace.
The drawbacks of this process are the need for a
pretreatment stage, in which the remainder materials
are agglomerated, and in the separately carried out
reduction and melting process, with the result that the
energy to heat up the remainder materials has to be
applied twice and a dedicated off-gas system is
required for each stage.

CA 02372809 2001-11-08
- 2 -
In a process which is described in DE-A-44 39 939,
remainder materials are melted down in a melting
cyclone, the heavy metals are vaporized and are
separated out of the off-gas as a dust fraction after
oxidation has taken place. The levels of heavy metals
in the slag which remains are further depleted in a
lower furnace by blowing on reducing gas and oxygen and
the slag is then used as a starting material for the
production of cement or rockwool. However, in this
process the iron is not reused, and consequently a
significant constituent of the remainder materials
remains unused.
One problem in the production of pig iron is the fine-
ore content, of which there are relatively high levels
and which is difficult to handle during the reduction
and smelting process. Consequently, the reduction of
the fine ore usually takes place in fluidized bed
reactors, which entail high levels of technical outlay.
Introducing the reduced fine ore into a melting furnace
also requires complex apparatus, the service life of
which is greatly restricted on account of the wear
caused by the reactivity of the iron sponge.
It is known from US-A-5,639,293 to carry out
preliminary reduction of iron ore by making the iron-
ore particles turbulent using oxygen and a reducing gas
in a melting cyclone and collecting the melted iron
particles in a metallurgical vessel beneath the melting
cyclone and then fully reducing them by blowing in
oxygen by means of a lance which projects centrally
through the melting cyclone and adding fuel, leading to
the formation of a reduction gas which rises into the
melting cyclone and, after it has reacted with the iron
ore, is extracted at the upper end of the melting
cyclone together with off-gases which form.
The cooling action of the oxygen lance which projects
centrally through the melting cyclone into the melting

CA 02372809 2001-11-08
- 3 -
vessel in accordance with US-A-5,639,293 may lead to
skull formation of the prereduced iron ore.
A device for reducing and melting down iron ore is
described in EP-A-0735146. According to EP-A-0 735 146,
iron ore is reduced and melted in a melting cyclone and
passes into a metallurgical vessel which directly
follows beneath the melting cyclone and in which, while
a process gas forms from coal which is blown onto the
slag/metal layer and oxygen which is blown in, the
final reduction and the complete melting of the iron
take place. The reducing process gas is partially burnt
with oxygen and, in this way, supplies the heat
required for the melting and reduction both in the
melting vessel and in the melting cyclone. The off-
gases are extracted at the upper opening of the melting
cyclone.
To separate slag and pig iron, the molten material
first has to be transferred into a settling vessel,
since in these known devices there is in each case only
one tapping hole in the lower vessel.
On account of the open melting cyclone base and the
associated lack of return flow in the melting cyclone,
the countercurrent guidance and the associated
turbulence of the reduction gas with respect to the
iron-ore particles leads to an increased level of
dusting, and this is made even worse by entrained slag
particles and leads to considerable discharges of
particles from the melting cyclone with the off-gas
which is discharged from the melting cyclone at the
top.
The invention aims to eliminate these drawbacks and
sets the object of providing a process and a plant
which make it possible to process iron-containing and
heavy-metal-containing remainder materials, in
particular from the iron- and steelmaking industry,

CA 02372809 2001-11-08
- 4 -
and, if appropriate, iron ore in an environmentally
friendly manner - avoiding landfill - so that the iron
can be utilized, i.e. can be used beneficially for
steelmaking. Furthermore, only a single off-gas flow is
generated, thus saving plant costs and minimizing
emissions, as well as increasing the possible
efficiency of energy recovery.
According to the invention, this object is achieved by
the combination of the following features:
- the remainder materials and, if appropriate, the
iron ore are introduced into a melting cyclone
with return flow,
- reducing agents and oxygen are additionally
introduced into the melting cyclone and are made
turbulent,
- in the melting cyclone, iron is reduced at least
to FeO,
- in the melting cyclone, heavy metals are reduced
to form metals and are converted into the gas
phase by vaporization,
- the resulting gas, which may contain heavy metals,
the partially reduced iron and the slag are
transferred into a directly coupled furnace,
- energy is supplied to the furnace,
- reducing agents and oxygen or oxygen-enriched air
are introduced into the furnace,
- iron is fully reduced and partially melted in the
furnace, and
- the vaporized heavy metals are precipitated
outside the furnace.
The meaning of the terms 'iron", 'iron-containing",
"heavy-metal" and "heavy-metal-containing" in each case
encompass both the corresponding metals in oxidized,
for example oxidic, form, and in reduced, i.e.
metallic, form, and specifically both in oxidized and
reduced form and in only one of the two forms; the
precise meaning becomes clear from the context.

CA 02372809 2001-11-08
_ 5 _
In this context, the term "reduction to Fe0" is always
to be understood as meaning reduction from trivalent to
divalent iron, i.e. from FeZ03 to 2Fe0, but also from
3Fe~03 to 2Fe304 ( i . a . to Fe203~Fe0) .
Furthermore, the use of a melting cyclone with return
flow, which is effected by a constriction in the base
of the melting cyclone, allows a low level of dusting
to be achieved. The iron-containing and heavy-metal-
containing remainder materials and, if appropriate, the
iron ore, on account of the return flow, achieve a
longer residence time in the melting cyclone and are
transferred into the furnace only in the liquid or
gaseous state. Even when the melting cyclone is
arranged above the furnace, slag particles are
prevented from entering the melting cyclone by the
constriction. Moreover, there is only one outlet
opening, which is provided in the bottom of the melting
cyclone, so that particles cannot be discharged by
means of a gas flowing upward through the melting
cyclone. According to the invention, all the materials
and gases which have been introduced into the melting
cyclone are forced to move into the furnace, where they
can be fully processed efficiently. This also has the
advantage of a single off-gas flow, namely from the
furnace, which accordingly can be treated easily and
inexpensively.
It is advantageously also possible to use fine ore as
iron-containing remainder material, in particular with
a proportion of extremely fine particles which
originate from the ore beneficiation or from the fines
from a pelletizing device.
The introduction of reducing agents, which are
advantageously introduced in solid, liquid or gaseous
form, and oxygen, preferably industrial-grade oxygen or

CA 02372809 2001-11-08
- 6 -
oxygen-enriched air, takes place horizontally,
preferably tangentially, into the vertically arranged
melting cyclone, with the result that the mass transfer
and heat exchange operations proceed very quickly.
Reducing agents and oxygen are added in controlled
quantities which are such that the heavy metals, during
the melting operation, are converted into the gas phase
by being vaporized in the metallic state, and the iron
is reduced at least to divalent iron oxide FeO.
The heavy-metal-containing gas, the partially reduced
iron and the slag are transferred into the furnace from
the melting cyclone by means of a connecting line which
is arranged between the bottom opening of the melting
cyclone and a furnace which directly follows the
melting cyclone, preferably through the top or through
a side wall of the furnace, and, if appropriate, via at
most one intermediate chamber which is arranged on the
wall of the furnace and allows particularly effective
separation of the melting zone from the reduction zone
in the furnace. The intermediate chamber into which the
connecting line opens may also be designed as a furnace
off-gas line.
To reduce the partially reduced iron which is present
in the form of divalent iron oxide in the molten
material to form metallic iron, solid reducing agent,
preferably coal or carbon-containing waste materials
(which are at least partially formed by fine
particles), is blown into the molten material with
oxygen or oxygen-enriched air. The step of blowing in
these substances may take place via below-bath blowing
nozzles or via lances which penetrate into the slag
layer floating on the molten metallic iron. For this
purpose the furnace is provided with openings for the
lances. The blowing nozzles are expediently partly
below the level of the metal bath and are connected to
feeds for reducing agents and/or oxygen. The lances may

CA 02372809 2001-11-08
- 7 _
be arranged in the furnace in any manner which is known
to the person skilled in the art.
On account of the difference in density, the reduced
metal droplets settle at the bottom of the furnace in
the molten metallic iron, and like the slag can
advantageously be tapped separately from the furnace,
continuously or discontinuously, via a dedicated
tapping hole.
In addition to the iron-containing and heavy-metal-
containing remainder material(s), which has/have been
melted down and prereduced in the melting cyclone, and,
if appropriate, iron ore, some coarse fraction may be
charged directly to the furnace, preferably via a
dedicated feed which opens into the furnace, for
example in the top or a side wall of the furnace.
To maintain the temperature which is required in order
to tap off slag and molten pig iron, energy is supplied
to the furnace, and this also prevents premature
separation of the heavy metals in the region of the
furnace. The energy is preferably supplied in the form
of electrical energy, for example via a direct arc, to
the molten material. It has proven particularly
advantageous for the electrical energy to be supplied
by means of at least one electrode projecting into the
furnace; both direct current and alternating current
are possible.
The evaporated heavy metals, together with the furnace
off-gas, are afterburned directly at the gas outlet,
with the result that the heavy metals are converted
into a solid oxidic form which, after separation from
the remaining off-gas in a precipitation device, can be
fed for further processing.
If the products originating from the melting cyclone,
namely heavy-metal-containing gas and molten material,

CA 02372809 2001-11-08
are firstly introduced into an intermediate chamber,
the heavy-metal-containing gas is introduced into the
furnace off-gas, which is extracted from the furnace
via the intermediate chamber, in this intermediate
chamber, whereupon the further treatment of the gases
takes place jointly.
The melting cyclone, the furnace vessel above the metal
level and, if appropriate, the intermediate chamber are
expediently equipped with evaporation cooling, with the
result that the radiant heat from the furnace and the
melting cyclone can be used to evaporate cooling water
and can therefore be recovered in the form of steam,
which can be used to save energy within a metallurgical
plant.
The same purpose is served by off-gas cooling,
preferably in a steam boiler, carried out following the
afterburning of the heavy-metal-containing gas and the.
furnace off-gas.
The utilization of the heat which is inherent to the
off-gas may advantageously also take place completely
or partially in a heat exchanger into which the off-gas
line of the furnace opens, it being possible to feed
the heated air to a dryer which dries iron-containing
and heavy-metal-containing, wet remainder materials or
slurries which are suitable for use in the melting
cyclone.
The invention is explained in more detail below with
reference to exemplary embodiments which are
illustrated in the drawing, in which Fig. 1 to 4 show
diagrammatic views of preferred embodiments of the
plant according to the invention.
In accordance with Fig. 1, coal, oxygen and iron-
containing and heavy-metal-containing remainder
materials and, if appropriate, iron ore in the form of
dust are introduced into a vertically arranged melting

CA 02372809 2001-11-08
_ g _
cyclone 1. The introduction takes place in such a
manner that the turbulence and the associated mass and
heat transfer processes in accordance with the
invention take place very quickly, with the result that
the melting and prereduction process overall has a high
space-time yield. The controlled release of the
substances which are to be introduced into the melting
cyclone 1 is effected by a metering device, which is
not shown but is known to the person skilled in the
art . The substances are blown into the melting cyclone
1 horizontally, preferably tangentially, via a
plurality of openings, which may be distributed over
the entire jacket of the melting cyclone.
Reduction of the iron-containing and heavy-metal-
containing remainder materials and, if appropriate, of
the iron ore takes place in the interior 2 of the
melting cyclone 1, iron being reduced at least to Fe0
and the heavy metals being reduced to the metal.
Furthermore, melting of the reduced iron-containing
material and conversion of the heavy metals into the
gas phase is achieved quickly and efficiently on
account of a cyclone-specific return flow.
An opening 3 in the bottom 4 of the melting cyclone 1
is formed by a constriction which causes the return
flow in the interior 2 of the melting cyclone 1 and
therefore allows minimal dusting to be achieved.
The melting cyclone 1 is directly connected to a
furnace 5 which is arranged beneath the melting cyclone
1. The melted products and the heavy-metal-containing
gas pass into the furnace 5 from above via a connecting
line 6.
In the furnace 5 there are a metal bath 7 (iron bath)
and a slag layer 8 which floats on the metal bath 7,
and these constituents are removed separately from the
furnace 5 via tapping holes 9 and 10. Furthermore,

CA 02372809 2001-11-08
- 10 -
according to this embodiment, the furnace 5 has three
electrodes 11, 11', 11" which are immersed in the slag
layer 8 from above and supply the energy which is
required to maintain a liquid slag 8 and a metal bath 7
S in the form of arcs. In this example, the electrodes
11, 11', 11" are operated with alternating current,
although operation with direct current would also be
possible, in which case the furnace 5 would have only
one electrode 11.
Reducing agent and/or oxygen is introduced into the
furnace 5 via below-bath blowing nozzles 12 in a side
wall 13 of the furnace 5 or in the bottom 14. Some of
the blowing nozzles 12 are preferably arranged below
the metal bath level.
In addition, in the embodiment shown in Fig. 1 there is
a lance 15 for blowing in coal and oxygen, which
projects obliquely into the furnace S through the side
wall 13 of the furnace 5 and the lower end of which is
immersed in the slag layer 8.
Moreover, a feed 16 for a coarse fraction of a reducing
agent or a remainder material which can be introduced
if appropriate opens into the furnace 5.
The iron-containing molten material which is introduced
into the furnace 5 from the melting cyclone 1 is fully
reduced in the slag layer 8 with the aid of the
reducing agent and the oxygen, and the liquid iron is
separated out into the metal bath 7.
On emerging from the furnace 5, air is fed to the off-
gas and afterburning 21 is initiated. Some of the
energy content of the off-gas, which has been increased
in this way, is transferred to water in a heat recovery
steam generator 17, the heat content of the off-gas
being used to generate steam. An example for the
further use of the steam is a turbine generator 18

CA 02372809 2001-11-08
- 11 -
which is used for current generation. However, other
possible uses for the steam which is generated are also
conceivable, for example use in the metallurgical plant
for cooling purposes, etc.
Following the boiler 17, the cooled off-gas is fed to a
filter 19, in which the condensed heavy metals, which
are in the form of dust, are separated from the
remaining off-gas.
The preferred embodiment illustrated in Fig. 2 differs
from the embodiment illustrated in Fig. 1 with regard
to the way in which the heavy-metal-containing gas and
the melted material from the melting cyclone 1 are
introduced into the furnace 5. In this embodiment, the
connecting line 6 opens out in the side wall 13 of the
furnace 5. The reducing agent and the oxygen are
introduced into the furnace 5 only via below-bath
blowing nozzles 12. The further treatment of the off-
gas after it leaves the furnace 5 is not shown in
further detail; it may take place in the same way as
that shown in Fig. 1.
In accordance with Fig. 3, the connecting line 6 opens
out in an intermediate chamber 20, which is designed as
an optionally widened (as illustrated by dashed lines)
off-gas line, so that the heavy-metal-containing gas
from the melting cyclone 1 does not need to flow
through the furnace 5, and the melted material is
already reduced further on the way into the furnace 5
by the reducing furnace off-gas . In this embodiment of
the plant according to the invention, the lance 15
which is used to blow in reducing agent and oxygen
projects into the furnace S from above. However, it may
also project through a side wall 13 into the furnace 5.
Fig. 4 shows the arrangement of melting cyclone 1 and
furnace 5 which is described in Fig. 1, but in this
case the heat which is inherent to the off-gas is only

CA 02372809 2001-11-08
- 12 -
partially utilized in the heat recovery steam generator
17. The off-gas which is still hot undergoes heat
exchange in a recuperator 22 and is then, in the cooled
state, passed into the filter 19, where the above-
described separation of the heavy metals takes place.
The air which is heated in the recuperator 22 is fed to
a dryer 23 which is used to dry wet remainder materials
and slurries for use in the melting cyclone 1.
The process sequence according to the invention is
explained with reference to the following Examples 1, 2
and 3. The quantity data are in each case based on one
tonne of charge mixture without coal or additives
(lime) .
Example 1:
1000 kg/h of iron-containing and heavy-metal-containing
remainder materials, which had a composition as shown
in Table 1, and 105 kg/t of coal were introduced into
the melting cyclone with 112 m3/t (s.t.p.) of deliver
air, and were made turbulent using 250 m3/t (s.t.p.) of
oxygen. 5.4 m3/t (s.t.p.) of fuel gas (natural gas)
were supplied in order to ignite the solid/gas mixture
in the melting cyclone and to maintain a pilot flame.
Table 1
Example 1 Example Example
2 3
Charge Unit Remainder- Remainder-Iron ore
mixture material mix material
1
without iron mix 2 with
ore iron ore
Chemical
analysis
-A1Z03 % by weight 0.67 0.90 0.63
-C % by weight 7.9 15.2 -
-Ca0 % by weight 5.5 5.1 3.0
-Fe % by weight 10.0 0.70 -

CA 02372809 2001-11-08
- 13 -
-Fe0 % by weight 34.4 20.1 -
-Fe203 % by weight 31.7 46.7 90.6
-Mg0 % by weight 1.69 1.1 0.36
-Mn0 % by weight - 0.10 0.17
-K + Na % by weight 0.15 0.24 0.04
-C1 + F % by weight 0.80 0.13 -
-Pb + Zn % by weight 0.30 1.7 0.01
-Si02 % by weight 3.13 3.6 4.0
-S % by weight 0.15 0.10 0.05
-P % by weight 0.15 0.10 0.05
The partially reduced iron was then fully reduced and
partially melted in the reduction furnace with 182 kg/t
of coal and 36 m3/t (s.t.p.) of oxygen. The amount of
delivery air for the solids blown in through lances or
nozzles was 45 m3/t (s.t.p.). The current consumption
of the furnace was 320 kwh/t.
576 kg/t of molten metal, 130 kg/t of slag and a
dedusted off-gas quantity of 12,140 m3/t (s.t.p.) were
obtained. 24 kg/t of heavy-metal-containing dust was
separated out of the off-gas. Furthermore, 737 kWh/t of
current were generated by utilizing the waste heat in a
steam generator.
The composition of the molten metal, of the slag, of
the off-gas and of the separated dust is given in Table
2. Examples 2 and 3 resulted in product compositions
which lay within the same range.
Table 2
Molten metal
-C % by weight 2.0 - 3.0
-Mn % by weight < 0.2
-Si % by weight 0.1 - 0.2
-S % by weight < 0.09
-P % by weight < 0.08
Slag
-Fe0 % by weight 3.0 - 6.0

CA 02372809 2001-11-08
- 14 -
-Ca0 % by weight 38 - 44
-Si02 % by weight 30 - 36
-Mg0 % by weight 7.0 - 12
-A1203 % by weight 5.0 - 10
Off-gas
-C02 % by volume 6.5 - 7.5
-02 % by volume 16 - 17
-Hz0 % by volume 1.0 - 1.5
-Nz + Ar % by volume Remainder
Dust
-Fe0 % by weight 30 - 75
-Zn0 % by weight 5 - 50
-Pb0 % by weight < 5.0
-Si02 % by weight < 5.0
-Ca0 % by weight < 7.0
Example 2:
A quantity of 1000 kg/h of iron-containing and heavy-
metal-containing remainder materials and iron ore - the
composition of the charge mixture is given in Table 1 -
with 56 kg/t of coal was introduced into the melting
cyclone by means of 106 m3/t (s.t.p.) of delivery air
and was made turbulent using 270 m3/t (s.t.p.) of
oxygen. 5.1 m3/t (s.t.p.) of fuel gas were supplied.
The amount of reducing agent (coal) introduced into the
furnace was 151 kg/t, the amount of oxygen was 30 m3/t
(s.t.p.) and the amount of delivery air was 38 m3/t
(s.t.p.). The current consumption was 268 kWh/t.
480 kg/t of molten metal, 125 kg/t of slag, 11,900 m3/t
(s.t.p.) of dedusted off-gas and 36 kg/t of heavy-
metal-containing dust were obtained. The current
production was 684 kWh/t.
Example 3:
The charge product used was 1000 kg/h of iron ore
(composition: Table 1) with 290 kg/t of coal and

CA 02372809 2001-11-08
- 15 -
136 m3/t (s.t.p.) of delivery air. Furthermore, 336 m3/t
(s.t.p.) of oxygen and 55 kg/t of lime were introduced
into the melting cyclone. The amount of fuel gas was
6.5 m3/t (s.t.p. ) .
To reduce the iron, 197 kg/t of coal were fed to the
furnace with 49 m3/t (s.t.p.) of delivery air and
38 m3/t (s.t.p.) of oxygen. The current consumption was
348 kWh/t.
The products obtained were 625 kg/t of molten metal,
139 kg/t of slag, 15,760 m3/t (s.t.p.) of dedusted off-
gas and 22 kg/t of dust. 945 kWh/t of current were
generated.

Representative Drawing
A single figure which represents the drawing illustrating the invention.
Administrative Status

2024-08-01:As part of the Next Generation Patents (NGP) transition, the Canadian Patents Database (CPD) now contains a more detailed Event History, which replicates the Event Log of our new back-office solution.

Please note that "Inactive:" events refers to events no longer in use in our new back-office solution.

For a clearer understanding of the status of the application/patent presented on this page, the site Disclaimer , as well as the definitions for Patent , Event History , Maintenance Fee  and Payment History  should be consulted.

Event History

Description Date
Application Not Reinstated by Deadline 2006-03-28
Time Limit for Reversal Expired 2006-03-28
Inactive: IPC from MCD 2006-03-12
Inactive: Abandon-RFE+Late fee unpaid-Correspondence sent 2005-03-29
Deemed Abandoned - Failure to Respond to Maintenance Fee Notice 2005-03-29
Inactive: Correspondence - Transfer 2003-01-28
Letter Sent 2002-12-12
Inactive: Single transfer 2002-10-25
Inactive: Cover page published 2002-05-01
Inactive: Courtesy letter - Evidence 2002-04-30
Inactive: Notice - National entry - No RFE 2002-04-26
Application Received - PCT 2002-03-20
National Entry Requirements Determined Compliant 2001-11-08
Application Published (Open to Public Inspection) 2000-11-23

Abandonment History

Abandonment Date Reason Reinstatement Date
2005-03-29

Maintenance Fee

The last payment was received on 2004-02-17

Note : If the full payment has not been received on or before the date indicated, a further fee may be required which may be one of the following

  • the reinstatement fee;
  • the late payment fee; or
  • additional fee to reverse deemed expiry.

Please refer to the CIPO Patent Fees web page to see all current fee amounts.

Fee History

Fee Type Anniversary Year Due Date Paid Date
MF (application, 2nd anniv.) - standard 02 2002-03-28 2001-11-08
Basic national fee - standard 2001-11-08
Registration of a document 2002-10-25
MF (application, 3rd anniv.) - standard 03 2003-03-28 2003-02-18
MF (application, 4th anniv.) - standard 04 2004-03-29 2004-02-17
Owners on Record

Note: Records showing the ownership history in alphabetical order.

Current Owners on Record
VOEST-ALPINE INDUSTRIEANLAGENBAU GMBH
Past Owners on Record
ALEXANDER FLEISCHANDERL
FRIED SAUERT
JOSEF PESL
Past Owners that do not appear in the "Owners on Record" listing will appear in other documentation within the application.
Documents

To view selected files, please enter reCAPTCHA code :



To view images, click a link in the Document Description column. To download the documents, select one or more checkboxes in the first column and then click the "Download Selected in PDF format (Zip Archive)" or the "Download Selected as Single PDF" button.

List of published and non-published patent-specific documents on the CPD .

If you have any difficulty accessing content, you can call the Client Service Centre at 1-866-997-1936 or send them an e-mail at CIPO Client Service Centre.


Document
Description 
Date
(yyyy-mm-dd) 
Number of pages   Size of Image (KB) 
Representative drawing 2002-04-30 1 9
Description 2001-11-08 15 639
Drawings 2001-11-08 4 51
Claims 2001-11-08 5 184
Abstract 2001-11-08 1 39
Cover Page 2002-05-01 1 54
Notice of National Entry 2002-04-26 1 194
Request for evidence or missing transfer 2002-11-12 1 105
Courtesy - Certificate of registration (related document(s)) 2002-12-12 1 106
Reminder - Request for Examination 2004-11-30 1 116
Courtesy - Abandonment Letter (Request for Examination) 2005-06-07 1 166
Courtesy - Abandonment Letter (Maintenance Fee) 2005-05-24 1 174
PCT 2001-11-08 10 377
Correspondence 2002-04-26 1 34